Is Your Project Over Budget? What You Need to Know About Value Engineering.
Is Your Project Over Budget? What You Need to Know About Value Engineering.
Value Engineering is NOT Cost
Cutting. If your team is only focused on stripping features or swapping quality
materials for cheaper ones, you're not doing VE—you're gambling with the
asset's lifecycle. Here’s the critical distinction every Owner and Project
Manager needs to understand before they panic.
Value Engineering
focuses on optimizing the overall value of a project by improving functionality
and reducing costs without sacrificing quality. Here's how Value Engineering is
typically applied in commercial retail design and construction projects:
Value Engineering Project Example:
A relevant example is the George R. Sweeney (Beaver Run) Water
Treatment Plant project outside of Pittsburgh, Pa. where we performed a
construction management agency contract with the Westmoreland County Water
Department.
Value Engineering Project Example:
A relevant example is the George R. Sweeney (Beaver Run) Water
Treatment Plant project outside of Pittsburgh, PA. We performed a construction
management agency contract for this project with the Westmoreland County Water
Department.
This was a $25 million, 25 MGD (million gallons per day) plant.
The Pennvest (Pennsylvania Infrastructure Investment Authority) loaned the
money for the plant to the Westmoreland County Water Department. Their stipulation
was that any project over $5 million would have to undergo a Professional Value
Engineering review.
We hired a Professional
Value Engineering team from Washington, D.C., to review the completed
engineering drawings that were designed by Gannett Fleming Engineers. The two
value engineers were familiar with water treatment plants in the areas of structural
design, plant process piping, and controls
Their review produced 163
Value Engineering suggestions. Following this initial review, we met with the Owner,
the Value Engineering team, and the Engineers of Record (Gannett Fleming) and
discussed the Value Engineering items in detail.
The Engineers' response was that, yes, we could do that; however,
their specification required us to build the tank, fill it with water, and then
observe the walls for leaks.
The Owner ultimately rejected this VE item, and we built the tank according to the original drawings.
Another Value Engineering (VE) item we discussed was the Equalization concrete structure, as you see here. This is a 50-foot by 50-foot by 20-foot high basin. The function of the equalization basin is to receive the sludge water from the cleaning of the clarifier beds and filter out the solids.
After they flood the
basin, they then drain it, and the sludge is subsequently shoveled out and
transported to the sludge drying beds. As you can see, the sludge is hosed down
the slope of the basin. Our VE item proposed that we could reduce the slope of
the basin, thereby reducing the overall structure by using less concrete in the
slope, floor, and walls. This VE item resulted in a $30,000 savings.
The Engineers' response was that while the slope could be reduced,
the Owner might incur an additional maintenance expense. With the steeper
original slope, workers could simply hose the sludge down. With the reduced
slope, however, they might have to manually squeegee the sludge, requiring
physical labor.
The Owner accepted this VE item.
The following is a list of the Value Engineering (VE) items that
we included in the Bid Packages and Purchase Orders:
Site Work VE Items
1. Reduce the paving section for plant access road.
2. Delete
shoring at the filter building and carbon building and lay back side slopes.
3. Substitute
pre-stressed concrete cylinder pipe for ductile iron pipe for raw water and
finished water mains.
Concrete Trade VE Items
1. Reduce
the percent slope of the concrete fill in the equalization basins, which will
reduce the concrete volume and allow the base slab elevation to be raised.
(Moderate redesign required)
Architectural VE items
1. Reduce
specified brick allowance.
2. Reduce
cast stone coping.
3. Delete
cast stone banding. Use accent brick.
4. Delete
ground-faced block. Use epoxy-painted C.M.U.
5. Delete
structural glazed face tile. Use epoxy-painted C.M.U.
Process Plant Piping VE Items
1
Allow the use of reinforced
concrete pipe instead of ductile iron pipe for clearwell and equalization basin
overflow lines.
2. Substitute
P.V.C. or C.P.V.C. material for stainless steel for air distribution piping in
the clarifiers.
3. Substitute
P.V.C. or C.P.V.C. material for influent distribution and relief piping in the
clarifiers. (Note: Section of piping through media bed to remain stainless steel.)
4. Substitute
fabricated steel piping for ductile iron process plant piping.
5. Delete
sluice gates at future ionization chambers in the clearwell
6. Delete
piping and valves for the clarifier by-pass. Install wall pipes necessary to allow
for future installation.
7. Delete
painting of PV.C. Piping.
8. Allow
substitution of cast cast-iron sectional boiler.
9. Substitute
P.V.C. or “Enfield acid resistant polypropylene piping materials for specified
silicon cast iron piping for lab waste system.
10. Substitute
A.S.T.M. D2513 Thermoplastic pressure for specified black steel pipe for size
gas piping.
11. Substitute
P.V.C. piping materials for the specified cast iron piping for the rainwater
conductor piping.
12. Consider the use of pressure-class ductile iron pipe for site drain lines instead of the Class
51 wall thickness specified.
13. Delete
magnetic site gauges for chemical storage tanks.
14. Delete
coating for P.C.C.P.
15. Substitute
carbon steel pipe materials for specified stainless steel piping for air blower
piping to the filters and clarifiers.
16. Substitute
wall-mounted chlorinators for the specified cabinet-housed chlorinators. All
other requirements of the chlorinators shall remain as specified.
17. Delete
the stainless-steel relief vent from the clarifier influent manifold as a
consequence of the use of Roberts Filter Company's “unrestrained” media beds.
Clarifiers VE Items
1. Consider
modular type filter bottoms (i.e., Universal Underdrain as manufactured by F.B.
Leopold Company) as a substitute for the specified muzzle and strainer type.
2. Utilize lower-grade stainless steel for D.A.F. system components.
HVAC
and Electrical VE items
1. Use
stainless steel ductwork instead of fiberglass ductwork.
2. Reduce
the requirements for the mounting of light fixtures.
3. Delete the light fixtures at the sludge drying beds.
Direct purchase of VE items
1. Sonic level transmitters.
2. Level
probes.
3. Ph
analyzers.
4. Venturi
meters
5. Turbidmeters
6. Use
“F” profile wall thimbles in place of “E” profile thimbles.
7. Direct
purchase capacitance type level transmitters.
8. Delete
telemetry via fiber optics to the existing Beaver Run plant.
9. Used a dedicated telephone circuit with a remote I/O rack.
10. Delete the shelf circulating pump.
11. Delete the shelf spare recycle pump.
12. Relocate the chlorine dioxide generator from the existing Beaver Run plant instead of purchasing
new equipment.
13. Delete
access manways to the chamber below the filter gullet due to the substitution of the filter
manufacturer.
14. Purchase
steel tanks from a steel pipe fabricator.
15. Delete
motor starters for the future raw water and high service pumps.
16. Delete
jib crane.
17. Delete
blower B.F. valves.
Roofing VE
Modify the specified roofing system. Reduce the roof insulation requirement. Consider the substitution of a specified vapor
retardant. Utilize a Gold Seal-warranted, ballasted E.P.D.M. System in place of a mechanically fastened E.P.D.M. System specified.
As I stated, we successfully hit the target budget of $25 million for the project, thanks to the Value Engineering items identified at the start.
The build took two and a half years, during which two severely harsh winters caused delays. These weather-related setbacks led to legitimate, compensable delay claims from several trades, resulting in total expenditures of just under $200,000. Looking at similar projects, it is wise to incorporate a contingency fund. This could be achieved by setting aside an equivalent amount—perhaps $200,000 of the accepted VE savings—to cover unforeseen costs.
Value Engineering
1. Cost Reduction: Identify ways to reduce costs while maintaining or improving
quality and performance.
2. Functionality Improvement: Evaluate the design and construction methods to
enhance the functionality and usability of the retail space.
3. Material Selection: Recommend alternative materials that provide the same or better
performance at a lower cost. Recommend alternative materials that provide the
same or better performance at a lower cost.
4. Collaboration: Work closely with architects, designers, and contractors to
ensure all aspects of the project align with value engineering principles.
Value Engineering (VE) is a critical aspect of all our projects, ensuring that the final outcome meets the desired standards of quality and efficiency while staying within budget. We integrate VE into all of our design-build projects, and we also apply it when reviewing a set of drawings already completed by a project owner.
In your experience, what is the most successful VE substitution you’ve seen that actually improved the building's function?
Share
your VE wins below!
Shettig Construction Management provides Professional Design-Build Construction Management services from the inception of your project through completion. www.shettig.com mshettig@gm
Comments
Post a Comment