Built to Last: Your Guide to Flawless Pier Foundations

 

Proper Pier Construction


The Structural drawings will show you the design of the piers.



Survey in the pier location as shown on the drawings. 

This must be done with extreme accuracy, using strings, batter boards, and a transit or laser level to ensure correct spacing and alignment.





Check the bell diameter and confirm that it is in compliance with the design.


Check the depth of the pier to confirm that it is per the design.




Water must be pumped out of the pier if it is more than 3” deep. If there is a lot of water, then you may have to perform a dewatering procedure. Consult with the engineer to determine the approved method of dewatering the area.


Install the specified reinforcing steel. Check it with the design drawings.


Provide a steel casing if need be. 


Remove the steel casing after the pour. 

 To eliminate failures on your next building project, ensure that your Construction Manager or General Contractor has a QC (Quality Control) program and that they adhere to it.

I wish you success on your project


Shettig Construction Management provides Professional Construction Management services from the inception of your project through completion. www.shettig.com

mshettig@gmail.com

 

Comments

Popular Posts

Build Faster, Smarter: Is the Design-Build Method Right for Your Project?

Building Smarter: The Power of Pre-Construction in Design-Build

Beyond the Dig: A Quality Control Checklist for Site Excavation