Pre-Engineered Metal Building Structural Inspections
Crane Setup and Location
Meet with your crane
operator and review a lifting plan before work commences.
Consider all the aspects of
the lift;
1)
Weight
2)
Center of
gravity
3)
Lifting points
on the load
4)
The path that
the load will travel during the lift.
5)
Review the capabilities
of the crane, review the load tables, or the instrument of loading.
6)
Consider the
wind
7)
Communication
during the whole process of the lift.
8)
Are the
outrigger pads a sufficient size?
Perform
a bearing capacity check by a geotechnical engineer for any crane or concrete pump
truck outrigger used on the project.
Set up a sequence plan for the erection of the building
1) Are all anchor bolts washered and properly nutted?
2) Is the steel plumb,
square, and aligned?
|
3) Are the required brace
rods tight with the necessary bevel washer
|
4) Do the base plates
align properly with the concrete?
|
5) Have all
connections been properly made and fully bolted according to the plans and specifications?
|
|
6) Are the high tensile
bolts in place and torqued as required?
|
7) Are the eave struts,
main building, and canopies straight and level?
|
8) Are the purlins and
grits properly made up and in good alignment without roll-over and with sag rods in place?
|
|
9) Have all component
parts, ridge sag rods, clip angles, haunch, flange braces, etc., as called for on the erection drawings, been properly installed?
|
|
10) Is the structural
Primer clean, with the shop coat in good condition, and any erection marks, burn, or smoke properly repainted?
|
|
11) Have the exposed
structural members without a shop primer been given a field coat?
|
|
12) Are the headers and
jambs for framed openings straight, unwarped, and erected plumb and square? Are the unused holes in the opening filled with bolts?
|
|
13) Was any burning or
welding, not on the erection drawings, necessary?
|
If yes, explain on the reverse side.
|
14) Are any structural
components bent, warped, or dented?
|
If yes, identify these
areas on the erection drawings.
|
15) Are structural
steel members free of dirt and dust? If not, power wash before erection.
SHEETING AND TRIM
|
1) Have the roof and wall
sheets been properly aligned, lapped, and fully fastened?
|
|
2) Have the fasteners been
over-driven?
|
3) Are any fasteners
loose?
|
4) Are any fasteners
missing?
|
5) Have the bottoms of
sheets been dented by improperly aligned base angle?
|
|
6) Do sheets or trim
show ladder scratches or other field damage?
|
7) Are all field cut
sheets clean, showing careful workmanship, and properly covered by trim or flashing?
|
|
8) Is all the trim in
place, neatly and carefully installed with all laps fastened and all joints and butts closely fitted?
|
|
9) Is the gutter straight;
do all the laps have sealant and are they adequately fastened?
|
|
10) Are there any
short sections of gutter or trim due to improper field cutting? |
|
11) Are the downspouts
according to plan, properly cut in and sealed, joined with the flow, neatly secured, and fastened to the high rib in a vertical line. Are the bottoms of elbows above the finished paving line, or properly lead into an underground drain?
|
|
|
12) Have proper
fasteners been used in applying the trim?
|
13) Has the roof been
swept, gutters cleaned, and roof and wall sheets cleaned of drill shavings?
|
|
14) Have scratches in the panel and trim been touched up and painted?
WEATHER ROOF
|
1) Has a sealant, when
required, been properly installed, and has loose mastic and paper backing been removed?
|
|
2) Have closure strips
been carefully installed and sealed where required?
|
|
3) Have LTP (Light transmitting panel), roof
vents, sheet cuts at openings, windows, thresholds, and any other points of possible leakage been carefully and neatly sealed with prescribed material?
|
|
4) Has the loose film been
removed from LTP?
|
|
5) Have the mitered eave
panels been properly caulked?
|
6) Are LTPs free of
cracks (especially at fastening points)?
INSULATION
|
1) Is the insulation
neatly installed according to standards for lapping and securing?
|
|
2) If used, has the mesh
wire been tightly stretched, properly secured, butt laps hidden behind purlins, and side laps made continuously?
|
|
3) Have you checked the insulation before installing it to ensure it is per the drawings?
|
|
4) Has the insulation been
folded back at the eave strut and around openings?
|
5) Has exposed
insulation at the bottom of wall sheets been lapped back to prevent wicking?
|
|
6) Have all punctures
or tears in the vapor barrier been properly sealed?
|
7) Have the proper
length fasteners been used for insulation thickness?
|
ACCESSORIES
|
1) Do all the accessories
with manual or mechanical movement operate freely and properly?
|
|
2) Do the walk doors fit
openings and latch properly?
|
3) Do the lock sets
operate?
|
4) Does the interlock
weatherstrip fit?
|
5) Is the glazing
complete?
|
6) Do the slide doors
operate freely? Are all guides in place? Is the latch properly aligned?
|
|
7) Do the overhead doors
fit and close; are keepers and lock sets properly adjusted, and is the tension correct?
|
|
8) Are all door keys
accounted for?
|
9) Is all the glazing
complete?
|
10) Are the latches
installed properly?
|
11) Are all the vent
dampers hooked up and operating properly?
|
OVERALL INSPECTION
|
1) Have the original
building plans and any changes been fully complied with?
|
|
2) Are all the openings
located according to the plan?
|
3) Are the side wall
sheets lapped away from the sheet-front of the building or prevailing winds>
|
|
4) Are all the fastener
lines straight and in the prescribed pattern?
|
5) Are all the building
lines proper, eave and rake lines,
|
openings, ridge, and
vents?
|
6) Has the proper touch-up of color imperfections on the sheets and trim been satisfactorily accomplished?
|
|
7) Have all mud, handprints, or other handling and erection marks been properly removed?
|
|
8) Has the construction
site been properly cleaned and cleared of debris?
|
|
9) Is flashing around
openings in the roof or between buildings and other collateral materials, such as masonry, glass, etc., proper, and correct?
|
|
|
10) Has the pre-engineered
building's primary or secondary steel been modified to accommodate a field change?
|
|
If yes, note on the erection drawing. I wish you success on your next building project. Leave a comment on what you would add to this list
|
Shettig Construction Management provides Professional Construction Management services from the inception of your project through completion. www.shettig.com
mshettig@gmail.com
|
|
|
Comments
Post a Comment